Top Finishing Layer

Asphalt / Bitumenious

  • 37.5 mm / 25 mm thickness.
  • Cleaning the ground surface by wire brush.
  • Applying taccoat.
  • Providing and laying premix bitumen carpet.
  • Rolling over it.
  • Sand or dust spreading over it.

RCC

  • 100 mm / 125 mm / 150 mm / 200 mm thickness.
  • Providing mixing and laying the cement concrete using the black trap, fine sand and 53 grade opc cement at the rate of 1:2:4.
  • Fixing the channels as per level.
  • Mixing and laying the material.
  • Using the Screed vibrator for better mixing after laying.
  • Finish the surface by power flotter and power trowel.
  • Using of Dewatering system pump for suction of the extra water if require.
  • Create the non sleepery surface for road and plain surface for internal flooring work.
  • Curing for 5 days.

Paved Block Work

  • M 15 / 20 / 30 / 40 grade – 60 mm / 80 mm thickness.
  • Sand filling on the sub base as per level.
  • Providing and laying Paved block as per size and grade.
  • Sand spreading over it.
  • Compaction by power compactor.

Curbing

  • 300 mm x 150 mm x 75 mm thickness.
  • 300 mm x 300 mm x 100 mm thickness.
  • 300 mm x 300 mm x 150 mm thickness.
  • Providing and fixing precast rcc block curbing of specified size using m15 concrate including excavation, bedding, fixing and pointing.